OAO Stroytransgaz was awarded a tender for construction of Yubileinaya Compressor Station (CS) of the gas pipeline Northern Regions of Tyumen Oblast (SRTO) – Torzhok.
Tuesday, March 22, 2005
OAO Stroytransgaz was awarded a tender for construction of Yubileinaya Compressor Station (CS) of the gas pipeline Northern Regions of Tyumen Oblast (SRTO) – Torzhok.
As a result of the bidding procedure, OAO Stroytransgaz was designated by the Tender Commission of OAO Gazprom as the general contractor for construction of CS Yubileinaya
(total capacity 75 MW).
Three companies were bidding in the tender for construction.
The Owner of the Project is ZAO Yamalgazinvest, an affiliate of OAO Gazprom.
Construction is planned to be started in the second half of 2005.
The time of construction is 14 months.
Reference
Construction and reconstruction of the gas transportation capacities of the cross country gas pipeline Northern Regions of Tyumen Oblast (SRTO) – Torzhok are a part of the “Plan for synchronization of commissioning of capacities of priority gas transportation projects to export gas supplies of OAO Gazprom through the gas pipeline Yamal-Europe for the years 2002-2006”.