December, 2010
Friday, December 17, 2010
Abu Dhabi, UAE – Stroytransgaz completed another phase of Taweelah–Fujairah Gas Pipeline Project in the United Arab Emirates (UAE).
Read more...
Tuesday, December 14, 2010
Moscow, Russia – Stroytransgaz installs equipment introducing “under stress” technology at the construction of HV line 750 kV Kalininskaya NPP–Gribovo.
Read more...
Friday, December 10, 2010
Beirut, Lebanon – S. Makarov, Chairman of the Management Board of Stroytransgaz, held a meeting with Gebran Bassil, Minister of Energy and Water of Lebanon.
Read more...
Monday, December 06, 2010
Moscow, Russia – On the 2nd of December 2010 Stroytransgaz was officially announced the winner in the tender bids for the execution of the work package for Reconstruction of 220 kV HV line Energia 3, 220 kV HV line Poshekhonie-Cherepovets 1, 220 kV HV line Pervomaiskaya, with overhangs to 750 kV Belozerskaya Substation, and reconstruction of 220 kV Outdoor Switchgear at 220 kV RPP1 Substation Project.
Read more...
Friday, December 03, 2010
Stroytransgaz has successfully passed an audit of its quality management system (QMS) for compliance with international standard ISO 9001:2008.
Read more...
Thursday, December 02, 2010
Moscow, Russia – Stroytransgaz continues to expand its activities in the field of electrical supply network construction. Stroytransgaz took part in the tender bids for the realization of HV line 500 kV Boguchanskaya Hydropower Plant–Ozernaya Substation Project, within the frames of development of the United Energy System (UES) of Russia.