The Headquarters for the Power Distribution Facilities Construction for Energy Block No. 4 of the Kalinin NPP Has Been Held
Wednesday, May 25, 2011
Volokolamsk, Russia – Today the meeting of the headquarters for the power distribution facilities construction for energy block No. 4 of the Kalinin nuclear power plant (KNPP) took place at the construction site of 750 kV Gribovo substation, Moscow region, and was guided by Oleg Budargin, Chairman of the Management Board of FGC UES. Sergey Makarov, Chairman of the Management Board of Stroytransgaz – the general contractor, senior management of FGC UES branch – Main Power Grids (MES) of the Centre, Engineering and Construction Management Centre of the Unified Energy System, and representatives of other contracting and engineering organizations also entered the conference. The participants discussed the coordination aspects of the contractors' activity in relation to the project carried out within the FGC UES investment program.
The 2011 November-December commissioning of main power grid facilities will provide the Moscow Energy System with additional 1,000 MW power capacity generating by a new energy block of Kalinin NPP. This will ensure new customers and increase the reliability of the energy system. The power grid facilities construction is completed according to the approved schedule and within the established deadline.
At present the installation of foundation and power transmission line supports is completed by 60% at the power distribution facilities; 58 km of wires are installed; construction and installation works are accomplished; and HV line 750 kV overhangs to the Kalinin nuclear power plant are prepared for energizing. In June SO UPS considers the possibility to connect new power line sections to the Unified National Electric Grid (UNEG).
The works for substations construction and equipment installation are being executed. In particular, 750 kV Gribovo substation under construction (Moscow region) with specified transformer capacity of 3,904 MVA is completed by 70%, the equipment foundation is near completion. The construction of 500 kV Dorokhovo substation is half-completed, the installation of equipment is under preparation.
The expansion of 750 kV Belozerskaya substation is under way in Vologda region. While construction and installation works are being carried out, the unique AT 750/500 kV autotransformer is being installed. The substation capacity will increase from 1,251 to 3,003 MVA due to the expansion.
The construction and upgrading of the power distribution facilities for energy block No. 4 of the Kalinin NPP is being implemented by application of innovative and energy-efficient technologies. In particular, the architectural look of the substations is improved; windows are fitted with I-glass, which allows cutting down the expenses on the substation facilities heating in winter. The junctions are equipped with red-spectrum neon lamps in order to prevent power line faults in darkness hours; fixed systems of infrared control over thermal condition detect the equipment faults at the early stages of operation that significantly reduce the substations repair period.
Totally, over 440 km of HV line 220-750 kV will be installed for the power distribution of the new energy block of the Kalinin NPP; more than 6,758 MVA of transformer capacity is put in operation.
Additional information:
The open joint-stock company Federal Grid Company of Unified Energy System (JSC FGC UES) is a largest infrastructure company with more than 79% of shares held by the Russian Government. The company operates 121 thousand of transmission lines, about 800 substations, facilities of the UNEG, and power grid facilities in 73 regions of the Russian Federation, with a total area over 13.6 million sq. km. The 2010 earnings are estimated at 111.1 billion RUR that exceeds the 2009 earnings by 30.6%, net profit – 58.1 billion RUR. In 2010 the electric energy supply equals to 470.65 billion kV/h.
PJSC Stroytransgaz is a major construction and engineering Russian company conducting its production activity in 17 countries. Stroytransgaz has been working in the energy construction market since 2006 and at present is carrying out nine projects in the heat and nuclear generation sector, including the starting complex of energy block No. 4 at the Kalinin nuclear power plant. The company also implements the UNEG projects for high voltage rating facilities construction.
Under the general contract for the construction of power distribution facilities for energy block No. 4 of the Kalinin nuclear power plant, Stroytransgaz will operate as the EPC contractor and implement commissioning and start-up.
Totally, over 440 km of 220-750 kV power lines will be installed for the power distribution of the new energy block of the Kalinin nuclear power plant, more than 6,758 MVA of transformer capacity will be put into operation. 750 kV Belozerskaya substation will be expanded, 500 kV Dorokhovo substation and 750 kV Gribovo substation are to be constructed along with 750 kV Kalinin NPP-Gribovo line, 500 kV Gribovo-Dorokhovo line, and the 220 kV Dorokhovo-Sloboda double-circuit cable overhead transmission line.