Dahej-Uran gas pipeline

In April 2006 Stroytransgaz, in a consortium with Gammon India Ltd., signed a contract for construction of the main section of the 108.8-kilometer Dahej-Uran trunk gas pipeline in India. The pipeline will provide gas to the country’s largest gas-powered electric generating station, which is located in Dabol. Customer for the project is GAIL Ltd.

Stroytransgaz is leader of the consortium. Its role includes project management, performing welding, and non-destructive testing.

The entire project consists of 395 kilometer in three sections: the first section, running 199 kilometers, has a diameter of 30 inches; the second, running 147 kilometers, has a diameter of 30 inches; the third, 108.8 kilometers, has diameters of 18 inches and 24 inches. There are also four gas pipeline branches with full length of 86 kilometers.

Construction of the main part of the gas pipeline was completed in 2007. The remained of the project was finished in 2008.