HV 500 kV Boguchany hydropower plant—Ozernaya substation
In November 2010 Stroytransgaz concluded a general contract for the construction of the HV line 500 kV Boguchany Hydropower Plant–Ozernaya Substation Project.
HV line 500 kV Boguchany hydropower plant–Ozernaya substation is anticipated for power distribution from the Boguchany hydropower plant and the external power supply for the Taishet aluminum plant. The route will pass along the territory of the Kezhem and the Boguchansk Rayons of Krasnoyarsk Krai and the Taishet Rayon of Irkutsk Oblast. The route length is 329.9 km, including 27 turning angles.
The customer for the project is CIUS UES, an associated company of FGC UES.
Stroytransgaz scope of work includes engineering and construction of the HV line and the related infrastructure, as well as the required materials and equipment delivery.
Construction is expected to be completed in 2012.