Kalinin nuclear power plant

Stroytransgaz has been chosen to participate in the Federal Target Program Development of the Nuclear Energy Industry of Russia for 2007–2010 and the Future to 2015. The company will carry out construction and assembly work for energy block №4 of the Kalinin nuclear power plant. Energy generating capacity of the facility is 1,000 MW.

The Federal Agency for Atomic Energy is customer for the project. Its general contractor is the federal governmental enterprise NIAEP. Stroytransgaz is primary subcontractor for the construction-assembly work at the start-up complex of the energy block (reactor compartment, turbine house, water pipeline, catch-water drain, and other facilities).

The nuclear power plant currently provides more than 60 percent of the electric energy produced in Tver Oblast. After energy block №4 enters exploitation in 2011, that indicator will rise to 67 percent.