South and North Gas Exploitation Project
In 2007 Stroytransgaz and the Syrian Gas Company signed a contract for construction of a gas processing plant in the central part of Syria. That contract was concluded on EPC terms.
The plant will have annual productive capacity of 1.1 billion m3 of purified gas, 20,000 tons of liquefied propane-butane, and 75,000 tons of condensate. The gas processing complex will be located 75 kilometers to the southeast of Al-Rakka
and 205 kilometers to the east of Homs, in the area where Syria’s larger hydrocarbon fields are concentrated.
Work on the project includes development of several gas fields: West Twinan, Twinan, Al Gour, East Al Akram, and Al Harith.
STG Engineering will carry out the engineering and procurement work.
The project is expected to be completed in 2009.